5 - PROJECT SCOPE MANAGEMENT






                   5.4.2.2 Expert Judgment


                      See Section 5.4.2.2 of the PMBOK  Guide.
                                                   ®

                   5.4.2.3 Activity-Oriented WBS

                      An example of an activity-oriented WBS is illustrated in this section of the Software Extension; it is descriptive
                   of an approach to creating a WBS for a software project; it is not intended to be prescriptive. The top level of an
                   activity-oriented WBS for a software project includes the full scope, at a high level, of all the work required to   5
                   complete the project successfully, as illustrated in Figure 5-3. The top level of an activity-oriented WBS is reflected
                   in, and can provide an input for refining the project scope statement. The subordinate levels can provide an input
                   for refining the product scope statement because the elements of work to produce the product components are
                   embedded in an activity-oriented WBS. The lowest level elements of work for the software construction activity of
                   the WBS produce specific deliverables. The tasks for Activity 3.2 in Figure 5-3 include work to reuse, construct, and
                   buy some software components. For brevity of presentation, the example includes only the subordinate elements
                   of Construct Software.

                      Embedding product scope in an activity-oriented software WBS is depicted in Figure 5-3, which illustrates a
                   partial WBS for developing the software for an automated teller machine; the product components are indicated in
                   bold font. The figure in Section 5.4.2.4 of this Software Extension illustrates further decomposition of the “Construct
                   FINAT” element of the WBS in Figure 5-3.




                                                               ATM Project






                                     1.          2.          3.         4.          5.         6.
                                   Manage     Analyze and  Construct   Verify     Validate    Deploy
                                    Project    Design     Software    Software    Software   Software






                                          3.1.        3.2.        3.3.       3.4.        3.5.
                                          Reuse     Construct   Construct    Buy       Integrate
                                         ATMSD       FINAT       MAIND      COMM        and Test
                                                                                     ATMSD, FINAT,
                                                                                     MAIND, COMM
                                                         ATMSD: Software Drivers
                                                       LEGEND  FINAT: Financial Transactions
                                                         MAIND: Maintenance & Diagnostics
                                                         COMM: Communication Package

                                         Figure 5-3. Partially Decomposed Activity-Oriented WBS