STEP 8: DOCUMENTATION AND DEVELOPMENT OF THE DEPLOYMENT PLAN 195
WEEKS: 1 2 3 4 5 6 7 8 9 10 11 12 13
WBS 1 Summary Element 1 57% complete
WBS 1.1 Activity A 75% complete
START-TO-START
WBS 1.2 Activity B 67% complete
FINISH-TO-START
WBS 1.3 Activity C 50% complete
FINISH-TO-FINISH
WBS 1.4 Activity D 0% complete
WBS 2 Summary Element 2 0% complete
WBS 2.1 Activity E 0% complete
WBS 2.2 Activity F 0% complete
WBS 2.3 Activity G 0% complete
Today
Figure 8.35 Sample implementation timeline.
Notification of deployment This section describes the method of notifying all
stakeholders of the successful release of all waste minimization programs and identi-
fies stakeholders and groups requiring notification.
Operations and maintenance plans This section describes the maintenance
and operations activities for each program or piece of equipment. For example, pre-
ventative maintenance schedules should be included for each new piece of equipment.
Contingency plan This section describes the contingency plan to be executed if
problems occur during deployment activities. A contingency plan is devised for spe-
cific situations if or when things do not occur as expected or circumstances change.
Contingency plans include specific strategies and actions to deal with specific vari-
ances to assumptions resulting in a particular problem, emergency, or state of affairs.
They also include a monitoring process and “triggers” for initiating planned actions.
They are very useful to help governments, businesses, or individuals to recover from
serious incidents in the minimum time with minimum cost and disruption.
Appendices This section contains all relevant appendices related to the project.
The alternative evaluation sheets should be included in this section.