Page 221 - Sustainable Cities and Communities Design Handbook
P. 221

Life Cycle Analysis Chapter j 10 195


             revenue requirements), the test results are unaffected by the uncertainties of
             projected average rates, thus reducing the uncertainty of the test results.
             Average rates and assumptions associated with how other options are financed
             (analogous to the issue of incentives for DSM programs) are also excluded
             from most supply-side cost determinations, again making the TRC Test useful
             for comparing demand- and supply-side options.


             Weakness of the Total Resource Cost Test

             The treatment of revenue shifts and incentive payments as transfer paymentsd
             identified previously as a strengthdcan also be considered a weakness of the
             TRC Test. While it is true that most supply-side cost analyses do not include
             such financial issues, it can be argued that DSM programs should include these
             effects since, in contrast to most supply options, DSM programs do result in
             lost revenues.
                In addition, the costs of the DSM “resource” in the TRC Test are based on
             the total costs of the program, including costs incurred by the participant.
             Supply-side resource options are typically based only on the costs incurred by
             the power suppliers.
                Finally, the TRC Test cannot be applied meaningfully to load building
             programs, thereby limiting the ability to use this test to compare the full range
             of DSM options.

             Formulas

             The formulas for NPV TRC , BCR TRC , and levelized costs are as follows:
                                  NPV TRC ¼ B TRC   C TRC

                                   BCR TRC ¼ B TRC =C TRC
                                    LC TRC ¼ LCRC=IMP
             where

                NPV TRC ¼ NPV of total costs of the resource
                BCR TRC ¼ BCR of total costs of the resource
                LC TRC ¼ Levelized cost per unit of the total cost of the resource (cents per
                kWh for conservation programs; dollars per kW for load management
                programs)
                B TRC ¼ Benefits of the program
                C TRC ¼ Costs of the program
                LCRC ¼ TRCs used for levelizing
                IMP ¼ Total discounted load impacts of the program
                PCN ¼ Net participant costs.
   216   217   218   219   220   221   222   223   224   225   226