Page 169 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 169

142    T h e Fe a s i b i l i t y S t u d y


             for the required level of accuracy when undertaken. By developing the LCC of each
             alternative under consideration (including the conventional or BAU case), one can
             determine the comparative advantage of the proposed system in terms of receiving the
             best economic return on the money invested (also called rate of return or internal rate
             of return). The following sections of this chapter explain in detail the components of
             an LCC analysis, and describe the process of performing an LCC analysis, including
             examples.
                The following sections define the economic terms for components of an LCC analysis,
             as well as explain how to estimate energy use and cost, estimate annual maintenance
             costs, estimate budget construction costs, and calculate life-cycle costs.

             Alternatives
             Alternatives are simply all of the options that are to be considered as part of the analysis.
             Typical alternatives for a combined heat and power (CHP) LCC consist of the BAU case
             (buying power from the local utility and fuel for thermal requirements) and multiple
             alternative cases using different types and sizes of equipment.
                The BAU case is the minimum that can be done to still satisfactorily meet the
             thermal and electric demands of the system. An example of a BAU case might be either
             using existing or installing new boilers and chillers to meet the facility thermal loads
             and purchasing electricity from the local utility to meet the electric loads of the facility.
             If existing equipment is planned to be used in the BAU case, consideration must be
             given to the age and condition of the equipment. If the equipment being used in the
             BAU case has a remaining useful service life less than that of the alternatives to which
             it is being compared, than replacement of the existing equipment must be factored into
             the LCC of the BAU case. Similarly, if the existing equipment will need major overhauls
             (outside of that to be considered in the annual maintenance costs), then those costs need
             to be factored into the LCC of the BAU case as well.
                The alternatives to which the BAU case is to be compared can be as few or as many
             as is desired. A keen understanding of CHP systems will help to eliminate alternatives
             that are not economically feasible prior to determining the LCC of the alternative. For
             example, if the project being considered has a relatively large electric load and a rela-
             tively small thermal load, then alternatives that provide considerably more thermal
             output than electric output should have already been eliminated from consideration
             during the conceptual engineering phase as the thermal load will be “dumped” on a
             regular basis as electric demand is met. Refer to Chap. 8 for additional information.

             Engineering Economics
             The concept of engineering economics can be summarized as the process to determine
             the best economic decision (e.g., the highest rate of return or the lowest LCC) given a
             number of alternatives which require technical knowledge and expertise in order to
             assess. While the economic concepts used are not unique to engineering economics, the
             ability to determine the “input” to economic formulas and criteria is unique to engi-
             neering economics. For example, assume one is focused solely on the economic aspect
             of a design decision and wants to estimate the annual cost savings, if any, from employing
             a CHP alternative in lieu of purchasing needed natural gas and electricity from local
             distributing public utilities. Accordingly engineering economics must be applied to cal-
             culate the technical components of the costs savings, such as energy use and cost and
             operation and maintenance requirements, for example.
   164   165   166   167   168   169   170   171   172   173   174