Page 265 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 265

238    C o ns truction


             to confirm emission rates of criteria pollutants such as NO , CO, ROG, SO , and PM
                                                                x            x
             (see  Chap. 7). In some cases, tests for specific hazardous air pollutants will also be
             required. Fuel analyses and fuel meter accuracy tests may also be required. The con-
             struction permit will most likely specify test methods to follow and time frames for
             completing the tests. Established test methods have been developed by various organi-
             zations including U.S. EPA, ISO, and ASTM International. Local environmental agen-
             cies may also develop test methods to be incorporated for projects in their jurisdiction.

             Coordinating the Emissions Test
             In some cases, the owner or developer will have full discretion in selecting a contractor
             to conduct the tests. In other cases, contractors may have to be certified by the regula-
             tory agency. Finally, in a few cases the regulatory agency will conduct the emissions
             tests themselves. If the agency is not responsible for conducting the test, the test
             contractor will submit a test plan for agency approval. The test plan identifies field test
             personnel, pollutants to be measured, test methods, sample repetition, and sample
             period duration. The plan also identifies CHP operating conditions, stack configuration
             (including sample port location) and anticipated emission concentrations. Once the test
             plan is approved, the contractor can proceed with the test program, but may be required
             to notify the agency several days in advance. Notification is intended to allow regu-
             latory agency personnel to witness the test and failure to notify the agency of an
             upcoming test could result in the test being disqualified.
                The developer will likely be responsible for coordinating various contractors, regu-
             lators, and the system operator to ensure that the CHP system will be operated for an
             adequate amount of time to complete the tests. Depending upon the test methods speci-
             fied by the regulatory agency, a test program may require from 1 to 10 (or more) hours
             to complete. The developer will have to ensure that the plant is capable of uninter-
             rupted operations to complete the test. It may also be necessary to operate the CHP
             system at various loads to complete the test. The developer may also encounter other
             logistical responsibilities such as providing adequate test facilities and ensuring that
             the emissions test does not interfere with other commissioning and start-up activities at
             the facility.

             Resolving Unacceptable Test Results
             Ideally, an emissions test will demonstrate that the new CHP system meets permitted
             emission limits. In these cases, the developer and permit holder can proceed to finalize
             operating permits and turn over the system to the operator. Unfortunately, start-up
             emissions tests sometimes do not demonstrate compliance with permit conditions and
             corrective actions must be initiated. Corrective action may include obtaining temporary
             relief from permit conditions or regulatory requirements while the conditions that cause
             excess emissions are resolved. At this point in commissioning, the developer must
             involve the permit holder because only the permit holder will be able to commit to any
             compliance agreements with the regulatory agency.
                To resolve unacceptable test results, the developer must understand what permit
             conditions or regulatory requirements may be violated. In some cases, a violation due
             to excess emissions may not occur until after the end of a period of 30 to 365 days. In
             these cases the developer may have time to correct the conditions that cause excess
             emissions and retest for emissions without ever being in violation. For example, a
             permit may limit PM emissions to a specified number of pounds per month, based
   260   261   262   263   264   265   266   267   268   269   270