Page 266 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 266

Operating Permits and Compliance Management Pr ograms        239


             upon a maximum operating schedule and assumed hourly emission rate; but the
             permit would not necessarily specify the hourly emission rate. If the test shows that
             PM emissions exceed hourly rate assumptions, the developer can project that continued
             CHP operations would result in a violation at the end of the 30-day period, but the
             system would remain in compliance until then because there are no short-term limits in
             the permit to be enforced. If prior to the end of the 30-day period the CHP is demon-
             strated through a second test to emit at a lower rate, or if the developer reduces the
             operating schedule to maintain compliance with the 30-day limit, no actual violation
             would occur and no relief from the permit would be immediately needed (although
             coordination with the regulatory agency is warranted).
                If the test results indicate emissions in excess of a concentration limit (ppmv or mg/m ),
                                                                                    3
             or a short-term mass limit (lb/h or kg/h), or a mass rate (lb/MW-h, or kg/MW-h), then
             the developer may have to temporarily shut down the CHP and the permit holder may
             have to seek temporary relief from enforcement of the permit or applicable regulation.
             Such relief can often be justified based upon the following conditions:
                 •  Economic hardship of not operating
                 •  Lack of alternative sources of power or heat to maintain facility processes or to
                    preserve goods in process
                 •  Critical public need for services supported by the CHP system such as hospitals,
                    wastewater treatment facilities, etc.
                 •  The need for system operations to identify the problem, and to subsequently
                    demonstrate compliance

             Regulators may also consider operator diligence and responsiveness when deter-
             mining if relief is warranted. It is critical to demonstrate that the violation was
             unforeseen and beyond the control of the operator. It is also critical to demonstrate
             that prompt action was taken to try to avoid noncompliance and to advise the regula-
             tory agency of the violation.
                The process of obtaining relief from construction permit conditions may be as
             simple as coordinating with regulatory agency staff. In many cases, agency staff and
             management have authority to enter into compliance agreements with the permit
             holder. These agreements are sometimes referred to as stipulated orders or stipulated
             agreements. In other cases, agency staff and management may be precluded from
             granting temporary relief from permit conditions or regulatory requirements. In these
             cases, the permit holder may have no choice but to petition for relief through a public
             hearing. During the hearing the developer and the regulatory agency would be allowed
             to present testimony regarding eligibility and the need for relief.

             Issuance of the Final Operating Permit
             Once all commissioning activities are complete and compliance with permit conditions
             are demonstrated, the developer, operator, and regulatory agency can proceed to con-
             vert the construction permit into an operating permit. This point of the permitting pro-
             cess may be the last time that simple administrative changes can be made to the permit
             without an application submittal or fee payment. It is also at this point that commis-
             sioning requirements will be deleted from the permit, leaving only ongoing compliance
             conditions that the operator will be required to meet.
   261   262   263   264   265   266   267   268   269   270   271