Page 168 - The Engineering Guide to LEED-New Construction Sustainable Construction for Engineers
P. 168

146    Cha pte r  F o u r



                                                          Responsibilities

                                             For EAp1 Only       For EAp1 and EAc3
          Tasks
          Designate commissioning authority   Owner or project team  Owner or project team
          (CxA)
          Document Owner’s Project           Owner or CxA design   Owner or CxA design
          Requirements                       team                team
                                             Owner or CxA design   Owner or CxA design
          Develop Basis of Design
                                             team                team or CxA design team
          Review OPR and BOD                 CxA                 CxA
          Incorporate commissioning requirements   Project team or CxA   Project team or CxA
          into the construction documents
          Conduct commissioning design review   n/a              CxA
          prior to midconstruction documents
          Develop and implement a            Project team or CxA  Project team or CxA
          commissioning plan
          Review contractor submittals applicable   n/a          CxA
          to systems being commissioned
          Verify the installation and performance   CxA          CxA
          of commissioned systems
          Develop a systems manual for the   n/a                 Project team or CxA
          commissioned systems
          Verify that the requirements for training   n/a        Project team or CxA
          are completed
          Complete a summary commissioning   CxA                 CxA
          report
          Review building operation within 10 months   n/a       CxA
          after substantial completion

        TABLE 4.0.2  Tasks and Primary Responsibilities for Commissioning per LEED-NC 2009 Reference Guide


                Intent
                Establish the minimum level of energy efficiency for the proposed building and systems.
                Requirements
                Design the building project to comply with both
                  •  The mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4) of ASHRAE/IESNA
                    Standard 90.1-2004
                And
                  •  The prescriptive requirements (Sections 5.5, 6.5, 7.5 and 9.5) or performance requirements
                    (Section 11) of ASHRAE/IESNA Standard 90.1-2004
                Potential Technologies and Strategies
                Design the building envelope, HVAC, lighting, and other systems to maximize energy
                performance. The ASHRAE 90.1-2004 User’s Manual contains worksheets that can be used to
   163   164   165   166   167   168   169   170   171   172   173