Page 296 - The Handbook for Quality Management a Complete Guide to Operational Excellence
P. 296

282   C o n t i n u o u s   I m p r o v e m e n t                                  D e f i n e   S t a g e    283


                                                Normal Schedule        Crash Schedule
                       Activity               Time (days)   Cost   Time (days)   Cost      Slope
                       Excavate               2            1000   1              2000      1000
                       Foundation             4            1600   3              2400        800*
                       Rough wall             10           7500   6              14000     1625
                       Rough electrical work   7           7000   4              14000     2333
                       Rough exterior plumbing   4         4400   3              6000      1600
                       Rough interior plumbing   5         3750   3              7500      1875
                       Wall board             5            3500   3              7000      1750
                       Flooring               4            3200   2              5600      1200
                       Interior painting      5            3000   3              5500      1250
                       Interior fixtures      6            4800   2              11000     1550
                       Roof                   6            4900   2              12000     1775
                       Exterior siding        7            5600   3              12000     1600
                       Exterior painting      9            4500   5              9000      1125
                       Exterior fixtures      2            1800   1              3200      1400

                      Table 13.7  Schedule Costs for Activities Involved in Constructing a House




                                                Crash schedule



                                             Project cost



                                                                            Normal schedule





                                                           Project duration
                                Figure 13.10  Direct costs as a function of project duration.



                                added to the direct costs, total costs will generally follow a pattern similar
                                to that shown in Fig. 13.11.
                                   To  optimize  resource  utilization,  the  project  manager  will  seek  to
                                develop  a  project  plan  that  produces  the  minimum  cost  schedule.  Of
                                course, the organ ization will likely have multiple projects being conducted
                                simultaneously, which places additional constraints on resource allocation.








          13_Pyzdek_Ch13_p265-292.indd   283                                                            11/9/12   5:14 PM
   291   292   293   294   295   296   297   298   299   300   301