Page 292 - The Handbook for Quality Management a Complete Guide to Operational Excellence
P. 292

278   C o n t i n u o u s   I m p r o v e m e n t                                  D e f i n e   S t a g e    279


                                   The slack time for an activity x,y is the difference between
                                    1.  The latest time of event y
                                    2.  The earliest time of event x plus the estimated activity time

                                   Slack time for an activity is the difference between the latest and earli­
                                est times for a given activity. Thus, assuming everything else remains on
                                schedule, the slack for an activity indicates how much delay in reaching
                                the  activity  can  be  tolerated  without  delaying  the  project  completion.
                                Slack times for the activities in the house construction project are shown
                                in Table 13.6.
                                   Events and activities with slack times of zero are said to lie on the
                                critical  path  for  the  project.  Conversely,  a  critical  path  for  a  project  is
                                defined as a path through the network such that the activities on this path
                                have zero slack. All activities and events having zero slack must lie on a
                                critical path, but no others can. Figure 13.8 shows the activities on the
                                critical path for the housing construction project as thick lines.

                                Control and Prevention of Schedule Slippage
                                Project managers can use the network and the information obtained from
                                the network analysis in a variety of ways to help them manage their proj­
                                ects. One way is, of course, to pay close attention to the activities that lie
                                on the critical path. Any delay in these activities will result in a delay for




                                      Activity                            Slack
                                      Excavate (1,2)                        2 - (0 + 2) = 0
                                      Foundation (2,3)                      6 - (2 + 4) = 0
                                      Rough wall (3,4)                    16 - (6 + 10) = 0
                                      Rough exterior plumbing (4,5)       20 - (16 + 4) = 0
                                      Roof (4,6)                          26 - (16 + 6) = 4
                                      Rough electrical work (4,7)         25 - (16 + 7) = 2
                                      Rough interior plumbing (5,7)       25 - (20 + 5) = 0
                                      Exterior siding (6,8)               33 - (22 + 7) = 4
                                      Wall board (7,9)                    33 - (25 + 8) = 0
                                      Exterior painting (8,10)            42 - (29 + 9) = 4
                                      Flooring (9,11)                     38 - (33 + 4) = 1
                                      Interior painting (9,12)            38 - (33 + 5) = 0
                                      Exterior fixtures (10,13)           44 - (38 + 2) = 4
                                      Interior fixtures (12,13)           44 - (38 + 6) = 0

                                    Table 13.6  Calculation of Slack times for House Construction Activities








          13_Pyzdek_Ch13_p265-292.indd   279                                                            11/9/12   5:14 PM
   287   288   289   290   291   292   293   294   295   296   297