Page 295 - The Handbook for Quality Management a Complete Guide to Operational Excellence
P. 295

282    C o n t i n u o u s   I m p r o v e m e n t                                                                                                                               D e f i n e   S t a g e    283



                                           Crash       Crash point
                                           cost



                                         Activity cost                             Normal point



                                          Normal
                                           cost



                                                    Crash                        Normal
                                                   duration                     duration
                                                                Activity duration
                                Figure 13.9  Cost-time relationship for an activity.




                                   For a given activity the cost per unit of time saved is found as

                                         (crash cost - normal cost)/(normal time - crash time)
                                   When  deciding  which  activity  on  the  critical  path  to  improve,  one
                                should begin with the activity that has the smallest cost per unit of time
                                saved. The project manager should be aware that once an activity time has
                                been reduced there may be a new critical path. If so, the analysis should
                                proceed using the updated information; that is, activities on the new criti­
                                cal path should be ana lyzed.
                                   The  data  for  the  house  construction  example  is  shown  below,  with
                                addi tional data for costs and crash schedule times for each activity.
                                   Activities  shown  in  bold  are  on  the  critical  path;  only  critical  path
                                activities are being considered since only they can produce an improve­
                                ment  in  overall  project  duration.  Thus,  the  first  activity  to  consider
                                improving would be foundation work, which costs $800 per day saved on
                                the schedule (identified with an asterisk [*] in Table 13.7). Directing addi­
                                tional resources toward this activity would produce the best “bang for the
                                buck” in terms of reducing the total time of the project. The next activities
                                for consideration, assuming the critical path doesn’t change, would be
                                excavation, then exterior painting, etc.
                                   As activities are addressed one­by­one, the time it takes to complete the
                                project will decline, while the direct costs of completing the project will
                                increase. Figure 13.10 illustrates the cost­duration relationship graphically.
                                   Conversely,  indirect  costs  such  as  overhead,  etc.,  are  expected  to
                                increase as projects take longer to complete. When the indirect costs are








          13_Pyzdek_Ch13_p265-292.indd   282                                                            11/9/12   5:14 PM
   290   291   292   293   294   295   296   297   298   299   300