Page 289 - The Handbook for Quality Management a Complete Guide to Operational Excellence
P. 289

276    C o n t i n u o u s   I m p r o v e m e n t                                                                                                                               D e f i n e   S t a g e    277




                                                     1     Start

                                                           Excavate (2 days)

                                                     2

                                                           Foundation (4 days)

                                                     3

                                                           Rough wall (10 days)


                                                     4     Roof (6 days)
                                                        Rough exterior
                                                        plumbing (4 days)
                                      Rough                                 6
                                     electrical
                                      work           5       Dummy (0 days)  Exterior siding (7 days)
                                     (7 days)
                                                        Rough interior
                                                        plumbing (5 days)
                                                                            8
                                                     7
                                                                             Exterior painting (9 days)
                                                        Wall board (8 days)
                                                                            10
                                           Flooring       Interior painting
                                           (4 days)  9    (5 days)
                                                                             Exterior fixtures (2 days)
                                             11              12
                                                   Dummy
                                                   (0 days)       Interior  13
                                                                  fixtures
                                                                  (6 days)
                                Figure 13.7  Network diagram for constructing a house.



                                precede the roof. The network diagram graphically displays the prece­
                                dence relationships involved in constructing a house. A PERT network
                                for constructing a house is shown in Fig. 13.7. (Incidentally, the figure is
                                also an arrow diagram.)
                                Finding the Critical Path
                                There are two time­values of interest for each event: its earliest time of com-
                                pletion and its latest time of completion. The earliest time for a given event
                                is the estimated time at which the event will occur if the preceding activ­
                                ities are started as early as possible. The latest time for an event is the








          13_Pyzdek_Ch13_p265-292.indd   276                                                            11/9/12   5:14 PM