276 C o n t i n u o u s I m p r o v e m e n t D e f i n e S t a g e 277
1 Start
Excavate (2 days)
2
Foundation (4 days)
3
Rough wall (10 days)
4 Roof (6 days)
Rough exterior
plumbing (4 days)
Rough 6
electrical
work 5 Dummy (0 days) Exterior siding (7 days)
(7 days)
Rough interior
plumbing (5 days)
8
7
Exterior painting (9 days)
Wall board (8 days)
10
Flooring Interior painting
(4 days) 9 (5 days)
Exterior fixtures (2 days)
11 12
Dummy
(0 days) Interior 13
fixtures
(6 days)
Figure 13.7 Network diagram for constructing a house.
precede the roof. The network diagram graphically displays the prece
dence relationships involved in constructing a house. A PERT network
for constructing a house is shown in Fig. 13.7. (Incidentally, the figure is
also an arrow diagram.)
Finding the Critical Path
There are two timevalues of interest for each event: its earliest time of com-
pletion and its latest time of completion. The earliest time for a given event
is the estimated time at which the event will occur if the preceding activ
ities are started as early as possible. The latest time for an event is the