Page 105 - The Six Sigma Project Planner
P. 105

Project Schedule Management
                    The Planner will provide two alternatives for project schedule management. The
                    traditional approach is to focus on individual activities. A relatively new approach,
                    called the critical chain approach, focuses on the project and the organization’s portfolio
                    of projects as integrated systems. Both methods have their proponents (and opponents)
                    and both are presented here. In all likelihood, the Six Sigma project team will be
                    required to follow the system practiced by its organization.
                    Traditional project schedule management involves a focus on activities. Status reports
                    are prepared by those responsible for the various activities. For each activity, these
                    reports include percentage completion, expected completion date, issues and plans to
                    overcome them, etc. Activity-based action plans are set in motion when activities are
                    substantially beyond their expected completion dates. The premise of this approach to
                    schedule management is that if activities are carefully monitored, the project due date
                    will take care of itself.



















































                                                             88
   100   101   102   103   104   105   106   107   108   109   110