viewed and approved by the proper personnel. Product configuration and drawing
                    change control systems are virtually universal in manufacturing organizations and
                    project teams may find a complete system, or at least a good template, in their
                    organization’s quality manual. Documented and implemented change control systems
                    are an ISO 9000 requirement.

                    Elements of Change Control Systems
                    For those who do not have access to a documented change control system, here’s a
                    checklist that can be used to develop a simple system.

                       •  As a general rule, the project team should develop the least restrictive system that will
                          ensure proper control of the project’s major documents. For many Six Sigma projects,
                          this will be a very simple and straightforward system.
                       •  Identify the control point—a key individual who will be the custodian of the
                          official version of the official project plan. This person will have password-
                          protected access to any electronic master documents.

                       •  How are change requests submitted? Which forms are to be used? To whom are
                          they submitted for approval?

                       •  Change requests should always include a “reason for change” section.
                          Information from this section should be reviewed periodically to identify
                          systemic problems and opportunities for improvement.
                       •  What will ensure that change requests are considered in a timely fashion?

                       •  How will the requestor be notified of the disposition of his or her change
                          requests?

                       •  The team should review the planner and list those documents in the planner that
                          will be subject to formal change control. Include only those documents for which
                          change control is truly necessary. (Note: Items in the Planner marked with an *
                          are generally considered to be part of the official project plan and candidates for
                          change control.)

                       •  For each controlled document, identify which members of the organization
                          and/or the project team will have the authority to approve a change.

                       •  In very specific terms, describe how changes will be incorporated into the official
                          plan. For example, are changes to be made to master documents using a
                          particular word processor? Is a special font used to denote changes?
                       •  How will changes be officially incorporated into the master documents?
                       •  How and to whom will revisions be communicated?

                       •  If multiple approvals are required, how is the change to be routed for approval?
                          Is a single document to be sent sequentially or will multiple review copies go out
                          simultaneously? How will comments from multiple reviewers be integrated into
                          the master document?