Page 21 - The Six Sigma Project Planner
P. 21

Table 1. Instructions for Completing the Project Charter Statement Form
                                         Field                      Contents

                                  Project             Enter a short title for the project. If your
                                  Name/Number         organization has a project numbering
                                                      system, include the assigned number.

                                  Sponsoring          Enter the name of the lowest-level
                                  Organization        organization that includes all processes
                                                      changed by the project. This organizational
                                                      unit must agree to sponsor the project.

                                  Project Sponsor     The sponsor should be the process owner
                                                      or line management at a level that can
                                                      allocate resources for the project.

                                  Project Black Belt   Enter the name and contact information of
                                                      the Six Sigma Black Belt assigned to this
                                                      project. If the project is being worked by a
                                                      team of Black Belts, enter the name of the
                                                    TEAMFLY
                                                      lead Black Belt responsible for the project.
                                  Project Green Belt   Enter the name and contact information of
                                                      the Green Belt project leader whose area is
                                                      most directly impacted by the project.
                                  Team Members        Enter the names and contact information of
                                                      the core team members.
                                  Principal           Enter the names and contact information of
                                  Stakeholders        the people, other than the sponsor, who
                                                      have a direct interest in the outcome of the
                                                      project. E.g., customer, supplier, functional
                                                      area manager, supervisor, responsible
                                                      engineering authority, union leaders, etc.
                                  Date Chartered      Enter the date that the charter was
                                                      accepted and signed by the sponsor.
                                  Project Start Date   Enter the date that the project is scheduled
                                                      to begin. Update when the actual start date
                                                      is known.
                                  Target Completion   Enter the date when the project’s
                                  Date                deliverables are expected to be completed.
                                  Revision            Charter revision tracking information.

                                  Sponsor Approval    Obtain the signature of the sponsor. Before
                                  Signature
                                                      signing, the sponsor should enter all
                                                      project-related meetings into his or her
                                                      schedule.



                                                                  ®