Page 30 - The Six Sigma Project Planner
P. 30

Score    Interpretation
                              3







                              1





                              0        Unclear or no benefit


                    3.0 Availability of Resources Other than Team
                              Score    Interpretation

                              9        Needed resources available when needed.
                              3        Limited or low priority access to needed resources.
                              1        Questionable resource availability.
                              0        Resources not available or excessive restrictions on access to
                                       resources.

                    4.0 Scope in Terms of Black Belt Effort

                              Score    Interpretation
                              9        Projected return substantially exceeds required return.
                              3        Projected return exceeds required return.

                              1        Projected return approximately equals required return.
                              0        Projected return not commensurate with required return.

                                                               6
                    Required return can be calculated as follows:
                    (1) Length of project (months) =

                    (2) Proportion of Black Belt’s time required (between 0 and 1) =

                    (3) Probability of success (between 0 and 1) =




                    6
                     Thanks to Tony Lin of Boeing Satellite Systems for this heuristic.