Page 30 - The Six Sigma Project Planner
P. 30
Score Interpretation
3
1
0 Unclear or no benefit
3.0 Availability of Resources Other than Team
Score Interpretation
9 Needed resources available when needed.
3 Limited or low priority access to needed resources.
1 Questionable resource availability.
0 Resources not available or excessive restrictions on access to
resources.
4.0 Scope in Terms of Black Belt Effort
Score Interpretation
9 Projected return substantially exceeds required return.
3 Projected return exceeds required return.
1 Projected return approximately equals required return.
0 Projected return not commensurate with required return.
6
Required return can be calculated as follows:
(1) Length of project (months) =
(2) Proportion of Black Belt’s time required (between 0 and 1) =
(3) Probability of success (between 0 and 1) =
6
Thanks to Tony Lin of Boeing Satellite Systems for this heuristic.
13