Page 32 - The Six Sigma Project Planner
P. 32
8.0 Project Charter
Score Interpretation
9 All elements of the project charter are complete and acceptable.
Linkage between project and deliverable is clear.
3 Project charter acceptable with minor modifications.
0 Project charter requires major revisions.
9.0 Value of Six Sigma Approach (DMAIC or Equivalent)
Score Interpretation
9 Six Sigma approach essential to the success of the project. Black
Belt/Green Belt skill set required for success.
3 Six Sigma approach helpful but not essential. Black Belt/Green
Belt skill set can be applied.
0 Usefulness of Six Sigma approach not apparent. Specific Black
Belt or Green Belt skills are not necessary.
15