Page 127 - The Toyota Way Fieldbook
P. 127

104                       THE TOYOTA WAY FIELDBOOK



                Case Example: Connecting Operations to Surface Waste
                in Engineering

                An automotive seat supplier had a very elaborate “phase-gate process”
                for developing new products. Each phase in the process of developing
                a vehicle had been defined in detail. The criteria for predefined “gates”
                for the product design was clear, and if upon review the design did not
                meet all those criteria, it would not pass to the next step in the process.
                This process was taught to everyone so they knew what to do in the
                process and when to do it.

                One of our associates worked with them as a consultant to develop a
                value stream map of the current process and discovered that it did
                not match the phase-gate process on paper very well (a common
                finding). There were constant delays causing backups in the system
                and no good flow. A future state vision was developed, and they
                went to work stabilizing subprocesses and then, somewhat crudely,
                connecting them together.
                One of the bottlenecks in the current state was the process of producing
                and testing prototypes. Seats were designed, parts were ordered, and
                hundreds of prototypes built and tested.
                When that process was mapped, it became clear that this was a classic
                case of batch and scheduled push (see Figure 5-10). All the seats were
                completely designed, including heated, not heated, bench, captain’s
                chairs, power, and so on. Based on the designs, parts were ordered.
                The parts arrived at various times from suppliers. The prototype group
                waited as long as they could for all the parts they needed and then
                started building whatever seats they could with the parts they had.
                Then they released lots of seats to testing. Seats that failed testing
                had to be redesigned to correct the problems.
                A future state map was developed. It became clear that the fundamental
                problem was batching. Each step in the process developed large batches
                and pushed to the next process. The inventory triangles in the current
                state diagram show the result—inventory. In the case of seat designs,
                it was an inventory of information—the designs—accumulating in front
                of parts ordering. The solution: Create a sequenced pull system. But




          Design                Order                    Build
          Seats        I         Parts      I         Prototypes      I          Test

        Figure 5-10. Current state map of prototyping process
   122   123   124   125   126   127   128   129   130   131   132