Page 161 - The Toyota Way Fieldbook
P. 161

138                       THE TOYOTA WAY FIELDBOOK


        much of a change would be needed to meet a hypothetical takt of 90 seconds
        per part. We see that two operations are currently over that estimated takt time.
            If these two operations were improved, how much improvement would
        be necessary before the next balance “plateau” is reached? Figure 6-9 shows the
        next plateau. Several other jobs have a cycle time of approximately 60 seconds.
        Reducing the two jobs to 60 seconds would allow the entire value stream to flow
        at a rate of one part every 60 seconds. Does that mean we should immediately
        pursue this goal? In fact if we do this and the takt time based on actual demand
        is greater than 60 second we will be over producing—the fundamental waste.
            After reducing the time it took for the two operations, it was determined that
        the actual takt rate necessary to meet the demand was 80 seconds. This allowed
        for “rebalancing” the operations and reducing their total number. In this case, after
        reducing the time it took to grind and buff, the total amount of work across all
        operations added to 645 seconds. If we divide 645 seconds of work by the takt
        of 80 seconds, we get a total of 8 operations at the takt time, compared to the
        original 12. Thus, we could reduce one-third of the operations by rebalancing to
        the 80-second takt.  If this were manual processes, it would equate to 4 fewer
        operators (note: these “extra” operators could be used to develop a team leader
        structure as outlined in Chapter 10). It is interesting to note that if we balanced
        to the faster takt of 60 seconds, 11 operators would be needed (645/60   10.75).
        Thus, going faster can cost more (provided it was not necessary to go faster).
            Use takt time to help make decisions about how the work will be designed
        and which improvements need to be made to meet the need. If you select a takt
        time that is too high, you will not meet the production need, which is worse
        than choosing a number that’s too low and exceeding the need (provided you did
        not add resources to meet the false need). It is always easier to stop production




                                      Line 1 Cycle Times
           120
                                                                   Takt Time = 90 seconds
           100
                         Next Plateau
            80
            60
            40
            20
             0                                          BUFF
                                                                    ATTACH COVER
          NOTCH/PIERCE  FORM 1  FORM 2 SPOT WELD STUD WELD SEAM WELD  GRIND  SPOT WELD FOOT WELD  LOAD




        Figure 6-9. Cycle balance chart showing next level plateau
   156   157   158   159   160   161   162   163   164   165   166