Page 190 - The Toyota Way Fieldbook
P. 190

166                       THE TOYOTA WAY FIELDBOOK


                had a goal for 25 jobs per day, so we set that as the volume target, even
                though the total amount of work varied. This variation, however, was
                handled by slight adjustment of the total work time each day and did
                not affect the workload balance throughout the day. The mix included
                two layers—the primary mix based on finish, and the secondary mix
                of components. The primary determination based on finish provided the
                correct mix to meet customer orders and workload, and the secondary
                provided the correct mix for workload. Sequence of the orders by finish
                helped to balance the workload, as did sequencing the components.
                These changes were the foundation for establishing standardized
                work and flow. Balancing the workload reduced the amount of line
                stoppage and smoothed flow throughout the rest of the operations.
                Future activities that connected operations reduced the “pile-ups”
                that frequently occurred.

                In a custom environment, it’s difficult to find an accurate measurement
                for performance. There is always an element of variation that will skew
                any measure. In this case, a longer view had to be developed, with the
                idea that over a wider time window (one month) the variation would
                be equalized. In other words, month over month we could begin to
                see improvement in performance as measured by total hours required
                versus total sales dollars. When performance was viewed over a six-
                month period, the variation was equalized even further, and there
                was a noticeable mean shift.



        Leveling Is an Enterprisewide Process
        The single most common reaction we get when we try to teach leveling to com-
        panies is: “Sales has their own incentives, and sales always comes first in this
        company. They sell whatever they can, and we in manufacturing are expected
        to build it, and sales can change by 100 percent or more from week to week.”
        When we’ve examined the data more carefully, we typically find that actual
        demand is much smoother than what manufacturing sees.
            In one office furniture manufacturing company that built a large variety of
        different filing cabinets, customer orders to the plant were unstable. Yet the cor-
        porate policy was 100 percent build to order, and manufacturing was constantly
        fighting fires to build whatever orders came  in. This led to huge amounts of
        inventory at every stage of production and no clear takt time anyplace in the
        process. When asked what lead times they gave customers who ordered filing cab-
        inets, the answer was six to eight weeks out. So the manufacturing plant was
        working like crazy to build orders that were all over the place, but there were six to
        eight weeks of nonvalue activities in the pipeline. Why couldn’t that time buffer
        be used to level the schedule? If there was inventory of finished filing cabinets, at
   185   186   187   188   189   190   191   192   193   194   195