Page 281 - Trenchless Technology Piping Installation and Inspection
P. 281

Pr oject Considerations for Pipe Replacement Methods       245

             In very soft or loose soils, significant ground movement may take
          place causing significant sags in the new pipeline and damage to
          nearby structures. In severe situations, the soil particles migrate to
          the interior of the existing pipe, converting the bursting operation
          into a piercing operation.
             Although there may be some plausible advantages in performing
          pipe bursting below the ground watertable—for example, possible
          reduced friction between the pipe and soil, as well as reduced effec-
          tive soil pressure on the pipe due to the buoyant force of the soil
          above—this situation presents significant problems. The groundwa-
          ter flows toward the insertion shaft, complicating the operation. Thus,
          in general, dewatering should be performed.


          6.8.5  Maximum Allowable Operating Pressure
          For pressure applications such as water, gas, and force mains, the
          maximum allowable pressure should be determined based on the
          maximum surge pressure that pipe will be subject to and the maxi-
          mum operating pressure for the pipe. The HDPE pipe should be
          designed to withstand the maximum allowable operating pressure
          (MAOP) and surge pressures according to conventional design pro-
          cedures, such as provided in the Plastics Pipe Institute’s Handbook of
          Polyethylene Pipe. DR 17 ∗  is typically used for bursting pressure or
          gravity pipe unless a higher pressure rating is required. In short,
          relatively shallow bursting runs, where high tensile and vertical
          forces are not expected, DR 21 may be used (see Sec. 6.10).


          6.8.6 Risk Assessment Plan
          It is important to pay close attention to the project surroundings
          (surface and subsurface conditions) to identify unfavorable condi-
          tions and possible risks. The risk conditions require extra attention in
          order to ensure the safety of the construction personnel and public, as
          well as surrounding facilities and infrastructure. Most underground
          and pipeline construction projects entail some risks due to unknown
          subsurface conditions. The risks associated with pipe bursting include
          damage to nearby facilities, failure to complete the project using the
          selected technology, and time and/or budget overrun. The risk of
          damage to nearby utilities, buried structures, and pavement increases
          under adverse soil conditions, improper construction techniques,
          design errors, inaccurate location of utilities, and the like. There are
          also risks associated with flow bypass, dewatering, shoring, and the
          like, if inappropriate procedures are employed. The additional risks


          ∗The dimension ratio (DR) of the pipe is the outer diameter divided by the wall
          thickness.
   276   277   278   279   280   281   282   283   284   285   286