Page 290 - Trenchless Technology Piping Installation and Inspection
P. 290

254    Cha pte r  S i x


                              Direction of insertion
           Polyethylene pipe
                       2.5 × D     12 × d
                                              Winch assembly


                                                   D



              Existing pipe with crown          D = Depth to invert
               removed to spring line
                                                d = Diameter of liner pipe
          FIGURE 6.10  Insertion shaft dimensions for HDPE pipe with DR 17.

             Acceptable arrangements for traffic control (based on DOT and
          local government regulations, and for the joined new pipe), with
          minimum inconvenience to nearby residents and businesses, must be
          carefully considered. The flow bypass pumping and pipe layout
          should be also planned. If it is necessary to dewater, safe and proper
          flow discharge plans are required. The contractor has, presumably,
          previously (see Sec. 6.8.9) submitted the jobsite layout plan that
          reflects the intended method of construction and addresses the above
          considerations. The contractor does not start the bursting operation
          before the engineer has reviewed and approved the jobsite layout
          plan. The site inspector enforces the adherence to this plan unless
          there is a valid reason for the deviation, and has been approved
          by the engineer or owner. If contaminated soil is excavated, the con-
          tractor must take the necessary measures for handling and disposal
          of the contaminated soil.

          6.9.2  Shoring the Entry and Pulling Shafts
          Proper shoring of the entry and pulling shafts is essential for the
          safety of the workers and the stability of the surrounding environ-
          ment. The trench shoring or bracing must be constructed to comply
          with Occupational Safety and Health Administration (OSHA) stan-
          dards. There are several available means of shoring these shafts:
          trench box, solder pile and lagging, steel sheet piles, corrugated pipes,
          and the like. In addition, if space is available, another option is to
          slope the sides of the shaft to provide stability. The judgment and the
          supervision of a competent person (as defined by OSHA) or a quali-
          fied geotechnical engineer is required to ensure the shoring is safe.
             In static pipe bursting method, the winch will thrust against the
          wall of the pulling shaft on one side. This side must be capable of
          withstanding the corresponding pressure. Since the pulling forces
          in static bursting applications are relatively high, in such cases the
          contractor should construct a thrust block to distribute the forces
   285   286   287   288   289   290   291   292   293   294   295