Page 291 - Trenchless Technology Piping Installation and Inspection
P. 291

Pr oject Considerations for Pipe Replacement Methods       255

          over a reasonably large area. The thrust block, shoring, and soil
          behind the shoring must be able to withstand the stresses from the
          pulling system. The passive earth pressure of the soil must exceed
          the stresses generated by the pulling system with an acceptable factor
          of safety.

          6.9.3  Matching System Components to Reduce
                 Risk of Failure
          One of the most critical activities prior to initiating the bursting project
          operation is to ensure that the system has sufficient power to burst
          the existing pipe segment between the insertion shafts to the pulling
          shaft. Additionally, the bursting system must overcome the friction
          between the soil and the outside surface of the new pipe with a rea-
          sonable margin of safety to account for unforeseen repair sleeves,
          clamps, and the like. In general, the bursting system components
          should be appropriately matched to the project; for example, the
          winch capacity should be compatible with the bursting head size and
          the conditions of the job.
             The contractor should adhere to the sizing guidelines stated in
          the operations manual issued by the bursting system manufacturer to
          match the system with the needs of the job. The manufacturer should
          be consulted if there is any doubt regarding the adequacy of the
          system for that specific run under those particular conditions (soil,
          depth, type of pipe, etc.). Lubrication of the outside surface of the
          new pipe with polymer or bentonite (depending on the type of soil)
          can reduce the coefficient of friction between the pipe and the soil,
          and consequently, reduce the required pulling force.
          6.9.4 Nearby Utilities
          The contractor must perform its due diligence to identify, locate, and
          verify the nearby underground utilities prior to digging the shafts
          and initiating the bursting operation. This includes contacting the
          local one-call center and request representatives of the utilities mark
          their existing lines on the ground surface. Then the contractor should
          then verify the exact location and depth of these utilities via careful
          hand digging and/or vacuum excavation. Manual excavation may
          be required within a few inches from the existing utilities to avoid
          damage. Vacuum excavation is an excellent tool to expose utilities
          with minimum surface excavation and minimum risk to the existing
          utility.
             Underground utilities that are in good conditions are unlikely to
          be damaged by vibrations at distances of greater than 2½ ft from the
          bursting head for small sizes (less than 12 in. in diameter), in soft
          soil, which is a typical application for pneumatic pipe-bursting
          operations (Atalah, 1998). The safe distance for large-diameter
          bursting (up to 24 in.) is about 7½ ft (see Sec. 6.8.7). These guidelines
   286   287   288   289   290   291   292   293   294   295   296