submitted by the contractor for the project. Record all information on the inspector report.
                               The liner wet-out report should be reviewed and matched to the liner material and resin,
                          Inspect the liner condition and verify that the delivered material is not damaged nor has


















                             prematurely exothermed before it is installed.



                                       and document on inspection report. Verify that homeowner notifications have been distributed as required in the contract documents  View CCTV inspection video of the existing pipe just prior to the installation of the liner by the  contractor. Note condition and cleanliness of pipe. Docum








                       Inspector Actions  •    •    •    •    •    •    •    inspection report.  •








                          Liner material delivered on site  Sample homeowner notification  Preinstallation cleaning and  CCTV inspection of the pipe  Pipe plugging or bypassing  Liner samples for testing  Monitoring CIPP cure  Inspector Action on Various Operations









                       Operation                    Traffic control  TABLE 7.7