Page 361 - Trenchless Technology Piping Installation and Inspection
P. 361

Inspection and QA/QC for Trenchless Installation and Replacement Methods   311

                 a week), until the pipe has been jacked between the speci-
                 fied limits.
              8.  If appreciable loss of soil occurs during the boring and jacking
                 operation, the voids must be packed promptly to the greatest
                 extent practicable with flowable fill (see DOT flowable fill
                 requirements).
               9.  The contractor must protect the excavation until the opera-
                 tion is complete and the excavation is backfilled.
          Overcut Allowance
          When using this method, the allowable overcut is 1 in. greater than
          the outside diameter of the pipe.

          Soiltight Joints
          Soil tight pipe joints are required to ensure the integrity of the road-
          bed. Pipe must be constructed to prevent earth infiltration through-
          out its entire length. Conventional pipe jacking is normally for use
          above the water table or for de-watered ground.
          Lubrication Fluids
          Lubrication fluids are required for this method of pipe installation to
          reduce jacking forces.
          Pipe Locating and Tracking

              1.  During construction, monitoring, and plotting, boring
                 progress must be undertaken to ensure compliance with
                 the proposed installation alignment and allow for appropri-
                 ate course corrections to be undertaken. Longer drives over
                 500 ft should have intermediate jacking shaft installed.
              2.  Pipe installed by this method must be located in plan as
                 shown on the drawings, and must be no shallower than
                 shown on the drawings unless otherwise approved.


          Jacking Force Calculation
               1.  The estimated jacking force must not exceed one-third of
                 specified allowable jacking capacity of the pipe to avoid pipe
                 damage.
              2.  The estimated jacking force must exceed the resistant force
                 required to install pipes with the microtunneling method.
              3.  Influential factors of the estimated jacking force include
                 •  Length of drive
                 •  Weight, grade, and diameter of the pipe
                 •  Height of the overburden
                 •  Soil characteristics
   356   357   358   359   360   361   362   363   364   365   366