Inspection and QA/QC for Trenchless Installation and Replacement Methods   315











































          FIGURE 8.4  Front and back of a microtunneling machine.

          be compatible with expected ground conditions. Contract specifica-
          tions must address (possibly through submittal requirements),
          methods for slurry disposal, lubrication, intermediate jacking sta-
          tions, shaft construction and MTBM entry and exit seals, installation
          monitoring, possible dewatering, and ground restoration, among
          other subjects.

          Preinstallation/Construction Planning
          Prior to construction, underground utilities must be located and visu-
          ally confirmed. A preconstruction survey must be made of the area to
          establish a damage and settlement baseline. A plan for addressing
          traffic control, handling and disposal of spoils, shaft construction and
          safety must be developed prior to beginning construction. Proper
          shaft construction is a key quality control issue. Groundwater and
          soil entry into the shaft must be controlled and minimized, especially