326     Cha pte r  Ei g h t









                                   Monitor




                                    LED target      Pilot head
                          Theodolite


          FIGURE 8.13  Line and grade control system. (Source: Bohrtec, 2008.)



















          FIGURE 8.14  Jacking frame. (Source: Bohrtec, 2008.)



             3.  Pilot tubes: The pilot tubes as shown in Fig. 8.15 are particu-
                 larly made of small sections so that they can be accommo-
                 dated in the shafts. The tubes shall rigidly connect to each
                 other, the steering tip, and the enlargement casing, and have
                 a clear inside diameter large enough to adequately view the
                 lighted target. The tubes shall withstand the torque encoun-
                 tered in the steering process.
             4.  Enlargement casing: The enlargement casing used  must be
                 strong enough and must have a diameter slightly larger than
                 the product pipe. The casing may match the product pipe but
                 by use of the newest powered reaming heads and powered
                 cutterheads only one casing is used for many larger product
                 pipe size. It must connect properly with the pilot tubes.
             5.  Soil-transportation system: The soil is transported through the
                 auger-system train, which is inside the casing.