14    Cha pte r  O n e




















































          FIGURE 1.10  (a) Worker entry EPBM. (b) Worker entry slurry machine.
          (Source: Pipe Jacking Association.)


          sections are transported inside the tunnel, and the annular space
          between the liner and the pipe is normally grouted. Due to separate
          phases of liner installation and pipe installation, the utility tunneling is
          called a two-step or two-phase operation, while conventional pipe
          jacking is called a one-step or one-phase operation. In general, person-
          nel are required inside the pipe to perform the tunneling and soil-
          removal operations. The main components of the utility-tunneling
          method are the same as conventional pipe jacking, except in the utility
   34   35   36   37   38   39   40   41   42   43   44