New Pipeline Installations    25














          FIGURE 1.19  PTMT operation, step 1: Installation of pilot tube. (Source:
          Bohrtec, 2008.)
















          FIGURE 1.20  PTMT operation, step 2: Insert auger casing. (Source: Bohrtec,
          2008.)

















          FIGURE 1.21  PTMT operation, step 3: Replace auger casing with product
          pipe. (Source: Bohrtec, 2008.)



             In step 2, the pilot tubes at the drive shaft are connected to a
          reamer with a diameter slightly larger than the diameter of the prod-
          uct pipe. Following the reamer is the auger casing, which helps in
          transporting the spoil back to the shaft. The spoil is then removed by
          a muck bucket or a vacuum truck, depending on the soil type. Step 2
          is complete when the reamer and the auger reach the reception shaft.
          This operation is shown in Fig. 1.20.