232    Chapter Eleven
         Exhibit 11-2
                              Item                                                        Included
         (Continued)
                               6. Issue a pass to all construction personnel on the site,
                                 with a number, the employee’s name, and the subcontractor
                                 for whom they work.
                               7. Keep a current list of all active personnel and passes that
                                 have been issued and are valid.
                               8. All material leaving the site must have a pass signed by
                                 the CM/GC.
                               9. Provide an after-hours construction entrance/exit for
                                 personnel.
                              10. File an incident report of any unusual activities at the site.
                              11. Obtain the contact information for the local police precinct,
                                 fire department, hospital, and first aid center in case of
                                 an emergency.
                              12. Post all emergency numbers in the CM/GC’s field office.
                              13. Maintain an emergency contact information directory for
                                 all the principals, foremen, and PMs for all the subcontractors
                                 working at the site.
                              14. Arrange for a roaming guard service to walk the site with
                                 a watchman’s key to observe the entire site during normal
                                 hours and after hours.
                              15. Arrange for the installation of closed-circuit television
                                 cameras at strategic locations to monitor personnel
                                 entering and leaving the site, deliveries, and removal of
                                 materials from the site.
                              16. File a police report for any criminal activities and prosecute
                                 all offenders.
                              17. Have the subcontractors store construction materials and
                                 tools in a safe and secure location.
                              18. Be especially careful to secure tools that can easily be
                                 removed and used in the home.
                              19. Security, like safety, is everyone’s responsibility.
                              20. Determine who will provide the security service to the
                                 site—the owner or the contractor?
                              21. Use the site logistics plan to determine the construction
                                 personnel entrance, owner’s entrance, construction
                                 materials, loading dock, etc., to determine the location and
                                 quantity of site access points and the number of security
                                 guards that will be required.
                              22. Establish an after-hours night and weekend entrance
                                 for access and egress to the site.
                              23. Provide a secure fence and gates around the site to secure
                                 it after hours.
                              24. Determine what additional security measures are
                                 required, such as closed-circuit cameras, motion detectors,
                                 security lock key systems, etc., and determine if
                                 the security company that is providing guard service
                                 can provide them.