                                                                                              9.7 Pressure and Leakage Tests of Water Mains
                                                                                            and fixture outlet protection. Follow up to ensure that
                                          state authorities and members of the local press and
                                          radio attend the meeting.
                                                                                            the recommended devices are installed and tested on
                                                                                            both an initial basis and a periodic basis consistent
                                       3. Place written notices of the pending cross-connection
                                                                                            with the cross-connection control ordinance.
                                          control program in the local newspaper and have the
                                          local radio station make announcements about the
                                                                                          The surveys should be conducted by personnel experi-
                                          program as a public service notice.
                                       4. Send employees who will administer the program
                                                                                      or owners’ representatives should be questioned as to what
                                          to a course, or courses, on backflow tester certifica-
                                                                                      the water is being used for in the facility and what haz-
                                          tion, backflow survey courses, backflow device repair
                                                                                      ards the operations may present to the water system (both
                                          courses, and so on.
                                                                                      within the facility and to the water distribution system) in the
                                       5. Equip the water authority with a backflow device
                                                                                      event that a backsiphonage or backpressure condition were
                                          test kit.                                   enced in commercial and industrial processes. The owners
                                                                                      to exist concurrent with a nonprotected cross-connection. In
                                                                                      the event that experienced survey personnel are not available
                                       6. Conduct meeting(s) with the local plumbing inspec-
                                                                                      within the water authority to conduct the survey, considera-
                                          tion people, building inspectors, and licensed
                                                                                      tion should be given to having a consulting firm perform the
                                          plumbers in the area who will be active in the inspec-
                                                                                      survey on behalf of the water department.
                                          tion, installation, and repair of backflow devices.
                                          Inform them of the intent of the program and the part
                                          that they can play in the successful implementation
                                          of the program.                             9.7 PRESSURE AND LEAKAGE TESTS OF
                                                                                      WATER MAINS
                                       7. Prior to initiating a survey of the established commer-
                                          cial and industrial installations, prepare a list of these  All external contaminations of water mains should be pre-
                                          establishments from existing records, then prioritize  vented. Contaminants entering the water mains through leaks
                                          the degree of hazard that they present to the water  are other types of cross-connections. Section 6.9.10 discusses
                                          system: plating plants, hospitals, car wash facilities,  the required separation of water mains from sources of con-
                                          industrial metal finishing and fabrication, mortuaries,  tamination. Even with proper separation of water mains from
                                          and so on. These will be the initial facilities inspected  pollution sources, all water mains must still pass the required
                                          for cross-connections; inspection of less hazardous  pressure and leakage tests to ensure that public health is pro-
                                          installations follows.                      tected. It is required to maintain a pressure of at least 20 psi
                                       8. Ensure that any new construction plans are reviewed  (140 kPa) at ground level at all points in the water distribution
                                          by the water authority to assess the degree of haz-  system under all conditions of flow. Unfortunately accidents
                                          ard and ensure that the proper backflow preventer  do happen due to human errors or unforeseen events. For
                                          is installed concurrent with the potential degree of  instance, more than one major fire or major pipe leaks or other
                                          hazard that the facility presents.          unanticipated high water demands might draw the hydraulic
                                                                                      grade line down to a point that a negative pressure (vacuum)
                                       9. Establish a residential backflow protection program
                                                                                      might be created at some service connections. This negative
                                          that will automatically ensure that a residential dual
                                                                                      pressure could potentially cause backflow from a contam-
                                          check backflow device is installed automatically at
                                                                                      inated source of water, if the pipe leaks. This section dis-
                                          every new residence.
                                                                                      cusses how the pressure and leakage tests can be conducted
                                      10. As water meters are repaired or replaced at resi-
                                                                                      to prevent any possible backflow from a contaminated source
                                          dences, ensure that a residential dual check backflow
                                                                                      of water.
                                          preventer is set with the new or reworked water meter.
                                          Be sure to have the owner address thermal expansion
                                          provisions.
                                                                                      9.7.1 Preparation for Pressure and Leakage Tests
                                      11. Prepare a listing of all testable backflow devices in the
                                          community and ensure that they are tested by certified  Pressure and leakage tests are usually conducted after the
                                          test personnel at the time intervals consistent with the  trench has been partially backfilled for a new pipeline. Same
                                          local cross-connection control ordinance.   tests can also be conducted frequently after an old pipeline
                                                                                      is being suspected of leakage.
                                      12. Prepare and submit testing documentation of back-
                                                                                          For a new pipeline installation, the pipe joints are often
                                          flow devices to the state authority responsible for
                                                                                      left uncovered until after the tests are completed. Each valved
                                          monitoring these data.
                                                                                      section of the water main is filled slowly with water, with air
                                      13. Survey all commercial and industrial facilities and  in the pipe being slowly released through corporation stops
                                          require appropriate backflow protection based on the  and hydrants. Corporation stop (or corporation cock) is a
                                          containment philosophy and/or internal protection  water service shutoff valve located at the street water main,