Page 115 - Well Control for Completions and Interventions
P. 115

Completion Equipment                                         107




















              Figure 3.16 Swell packer.


              They are have largely replaced ECPs as the method of choice for open
              hole multiple zone completions, where they are used to provide isolation
              between zones. They are also used as an alternative to cemented and per-
                          6
              forated liners, and have been used at the liner top as a cement assurance
              tool (Fig. 3.16).






                   3.5 WIRELINE ENTRY GUIDES

                   The wireline entry guide (WEG) or mule shoe is commonly used
              at the bottom of a tubing string. It has two functions. To guide the tubing
              into a liner top PBR or packer seal bore, and to guide through tubing
              intervention tools back into the tubing. To perform these functions, a
              properly designed WEG should have internal and external tapers. Some
              entry guides are “self-indexing.” These self-indexing mule shoes make it
              easier for seals to engage in a PBR in deviated wells.






                   3.6 LINER TOP SEAL ASSEMBLY

                   A liner top seal is constructed from a series of chevron (V) packing
              stacks or bonded seals mounted on a flow mandrel (Fig. 3.17).