Page 274 - Fluid Power Engineering
P. 274

Deploying W i nd T urbines in Grid  241


                    estimates for interconnection. It includes a power flow and
                    short-circuit analysis. In the United States, a deposit of $10,000
                    is required to initiate the study, which is performed by the
                    RTO or its consultants. It must be completed in 45 days after
                    a completed application has been received; RTO may seek an
                    extension by providing a reason to the customer.
                    System impact study: This is a detailed transmission planning

                    study to understand the impact of the proposed wind farm on
                    existing transmission, generation, and customers. The analy-
                    sis performed includes, impact on short-circuit power, dy-
                    namic and stability issues, protection systems, safety and
                    reliability of transmission, and any other adverse impacts on
                    the system. The deliverable is a written report on improve-
                    ments to the transmission system, and estimated cost. In the
                    United States, a deposit of $50,000 is required; the study is
                    performed by the RTO. This study must be completed in
                    90 days; however, if a cluster or group study is performed,
                    then an additional 90 days is available.
                    Facilitystudy:Thisisadetailedengineeringstudytodesignthe

                    interconnection substation and transmission and to provide
                    estimates for the cost and time to implement the upgrades.
                    In addition, it delineates the responsibilities of the wind farm
                    developer and the local transmission company to upgrade
                    transmission. In the United States, the study is normally per-
                    formed by the local utility for the RTO; it requires a deposit
                    of $100,000. This study should be completed in 90 or 180 days
                    depending on accuracy of cost estimates requested, ±20 or
                    ±10%, respectively.


                 In all three studies, a refund is issued or additional charges are
              billed based on the actual cost of the study. An interconnection re-
              quest is inserted into a queue and time to process the request varies
              from region to region. The timeframes specified above are based on
              FERC guidelines. Prerequisite to an interconnection application are
              access to land either through ownership or lease agreements. The in-
              terconnection will require a developer to choose between two types of
              services: Energy resource interconnection service (ERIS) and network
              resource interconnection service (NRIS). An ERIS has a much lower
              bar because it does not require any transmission system upgrades. It
              allows a generation to interconnect in order to deliver output using
              existing firm or nonfirm transmission capacity on an “as available”
              basis. NRIS requires a complete network analysis, while treating the
              proposed wind farm as a network resource comparable to any other
              large generation facility. In this analysis, the system is analyzed at
              peak load and under a variety of stressed conditions to ensure that
              the proposed generation facility operating at full capacity along with
   269   270   271   272   273   274   275   276   277   278   279