Page 273 - Fluid Power Engineering
P. 273

240   Chapter Eleven


                    Loading on WTST is considerably more cyclical than tradi-

                    tional transformers. The thermal cycling caused by varying
                    load can cause damage to insulation and to internal and ex-
                    ternal connectors.
                    Imperfect sinusoidal waveform because of power electronics

                    converters cause additional loading. If high-frequency filters
                    are not used, then electrostatic shielding may be required to
                    prevent transfer of harmonic frequencies to the higher voltage
                    side.
                    Ability to withstand low-voltage ride-through (LVRT) re-

                    quires that transformer be able to handle full short-circuit
                    current for at least 0.625 s. During such a transient period,
                    the transformer experiences high mechanical forces.


        Wind-Plant Interconnection and Transmission Study
              Wind farms that deliver power into the utility grid are required to
              submit to an interconnection study that is performed, in most coun-
              tries, either by the local utility or a regional transmission organization
              (RTO) or a regulatory agency. The description of the various studies
              and agreements in this section is specific to the United States, although
              most countries have similar processes. Furthermore, the intent of this
              section is not to be comprehensive, since there are variations to the
              process from one country to another and within a country from one
              region to another.
                 An interconnection agreement only provides the right to connect
              tothetransmissionline;itdoesnotprovidetherighttotransmitpower.
              A separate transmission agreement is required. Interconnection and
              transmission agreements do not guarantee that a utility will buy the
              energy; a power purchase agreement is required with a buyer to sell
              the energy produced in the wind farm. The interconnection study, as
              practiced in the United States, is separated into two types:

                    Large generator interconnection request (LGIR) for 20 MW or

                    more
                    Small generator interconnection request (SGIR) for less than

                    20 MW with a request for energy resource service

                 LGIR is a three-step process. Although the following process is
              specific to United States, most other countries have a variation to the
              following process: 18,19,22


                    Feasibility study: The primary purpose is to check if the system

                    can accept power injection at the interconnect point chosen
                    by the wind farm developer, and to provide high-level cost
   268   269   270   271   272   273   274   275   276   277   278