Page 288 - Fluid Power Engineering
P. 288

254   Chapter Twelve


                    impact on wildlife is not significant, then the permitting pro-
                    cesses is begun. If significant impacts are identified, then the
                    question that is addressed is: Can the impacts be mitigated? If
                    the answer is yes, then plans are developed to mitigate and the
                    permitting process is begun. After the permit is obtained, con-
                    struction can begin. A list of best management practices for
                    site development and construction are presented in the guide-
                    lines. These can ensure that the potential impact is minimized
                    during the construction phase.
                  Tier 4: Postconstruction fatality studies. This tier is performed
                    if required by any of the tier 1–3 studies. The activities per-
                    formed in this tier include search for bird and bat carcasses,
                    classify finding based on species, compare actual fatalities
                    with predicted, and analyze variation of fatalities based on
                    turbine location within the project site.
                  Tier 5: Other postconstruction studies. This tier is performed in
                    cases when (a) the actual fatalities are higher than predicted
                    in tier 3 and/or the mitigation strategies implemented are
                    ineffective, and (b) the fatalities measured in tier 4 are likely
                    to cause a significant impact on the population. This tier is
                    costly and should be performed in rare cases. The intent of
                    the recommended guideline is to ensure that tier 1–3 are done
                    with enough rigor that a project is not in a situation in which
                    tier 5 is required.
              In order to perform preliminary wildlife assessments, few states in the
              UnitedStatesprovideonlinetoolsthatprovideaninventoryofspecies.
              The State of Illinois Department of Natural Resource has an online
                                                                  6
              application, Ecological Compliance Assessment Tool (EcoCAT) , that
              provides a list of protected natural resources in and around an area of
              interest.


        Noise from Wind Turbines
              Noise is a form of pollution generated by turbines. However, the im-
              pact of sound is limited to a few hundred meters from the base of a
              turbine. Noise is generated in a turbine from two primary sources:
                  1. Aerodynamic interactions between the blades and wind. This
                    is the persistent “whoosh” sound as the blades slice the wind.
                    This is the dominant noise from a turbine.
                  2. Mechanical noise from different parts of the turbine, like gear-
                    box and generator.

                 Sound is a pressure wave. A unit of measure for sound is decibels.
              Sound level is quantified as ten times the logarithm of the ratio of
   283   284   285   286   287   288   289   290   291   292   293