Page 104 -
P. 104
4 - PROJECT INTEGRATION MANAGEMENT
The project management plan may be either summary level or detailed, and may be composed of one or more
subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the
project management plan is baselined, it may only be changed when a change request is generated and approved
through the Perform Integrated Change Control process.
While the project management plan is one of the primary documents used to manage the project, other project
documents are also used. These other documents are not part of the project management plan. Table 4-1 is a
representative list of the project management plan components and project documents.
table 4-1 differentiation Between the Project Management Plan and Project documents
Project Management Plan Project Documents
Change management plan Activity attributes Project staff assignments
Communications management plan Activity cost estimates Project statement of work
Configuration management plan Activity duration estimates Quality checklists
Cost baseline Activity list Quality control measurements
Cost management plan Activity resource requirements Quality metrics
Human resource management plan Agreements Requirements documentation
Process improvement plan Basis of estimates Requirements traceability matrix
Procurement management plan Change log Resource breakdown structure
Scope baseline Change requests Resource calendars
• Project scope statement
• WBS
• WBS dictionary
Quality management plan Forecasts Risk register
• Cost forecast
• Schedule forecast
Requirements management plan Issue log Schedule data
Risk management plan Milestone list Seller proposals
Schedule baseline Procurement documents Source selection criteria
Schedule management plan Procurement statement of work Stakeholder register
Scope management plan Project calendars Team performance assessments
Stakeholder management plan Project charter Work performance data
Project funding requirements Work performance information
Project schedule Work performance reports
Project schedule network diagrams
78 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition
®
Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
This copy is a PMI Member benefit, not for distribution, sale, or reproduction.