4 - PROJECT INTEGRATION MANAGEMENT






                      4.5.1.4 Enterprise Environmental Factors

                         Described in Section 2.1.5. The following enterprise environmental factor can influence the Perform Integrated
                      Change Control process: project management information system. The project management information system
                      may include the scheduling software tool, a configuration management system, an information collection and
                      distribution system, or web interfaces to other online automated systems.


                      4.5.1.5 organizational Process Assets

                         Described in Section 2.1.4. The organizational process assets that can influence the Perform Integrated Change
                      Control process include, but are not limited to:

                            •   Change control procedures, including the steps by which official organization standards, policies, plans,
                              and other project documents will be modified, and how any changes will be approved, validated, and
                              implemented;
                            •  Procedures for approving and issuing change authorizations;
                            •   Process measurement database used to collect and make available measurement data on processes
                              and products;

                            •   Project documents (e.g., scope, cost, and schedule baselines, project calendars, project schedule network
                              diagrams, risk registers, planned response actions, and defined risk impact); and

                            •   Configuration  management  knowledge  base  containing  the  versions  and  baselines  of  all  official
                              organization standards, policies, procedures, and any project documents.


                      4.5.2 Perform Integrated change control: tools and techniques



                      4.5.2.1 Expert Judgment

                         In addition to the project management team’s expert judgment, stakeholders may be asked to provide their
                      expertise and may be asked to sit on the change control board (CCB). Such judgment and expertise are applied to
                      any technical and management details during this process and may be provided by various sources, for example:






















             98       ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   119   120   121   122   123   124   125   126   127   128   129