Page 163 -
P. 163

5 - PROJECT SCOPE MANAGEMENT












                                                        Project Scope Management

                                                         5.2
                                                        Collect
                                                      Requirements
                                                                   • Requirements              Project
                                  Enterprise/                       documentation            Documents
                                  Organization                     • Requirements                                         5
                                                                     traceability matrix
                                                • Organizational          • Project documents
                                                  process assets            updates             4.2
                                    4.2                                                     Develop Project
                                 Develop Project                  5.6                        Management
                                      • Project
                                  Management    • Project        Control  • Project management  Plan
                                                                            plan updates
                                                  management plan
                                    Plan   charter               Scope
                                                • Work performance        • Work performance
                                                  data                       information        4.4
                                                                                             Monitor and
                                    4.3                                                      Control Project
                                  Direct and                                                   Work
                                 Manage Project                         • Change
                                    Work                                   requests
                                                                                                4.5
                                                                                               Perform
                                                                                              Integrated
                                                                                            Change Control
                                                                   • Organizational process
                                                                     assets updates
                                                                                              Enterprise/
                                                                                             Organization

                                              Figure 5-17. control Scope data Flow diagram

                      Controlling the project scope ensures all requested changes and recommended corrective or preventive actions
                   are processed through the Perform Integrated Change Control process (see Section 4.5). Control Scope is also used
                   to manage the actual changes when they occur and is integrated with the other control processes. The uncontrolled
                   expansion to product or project scope without adjustments to time, cost, and resources is referred to as scope
                   creep. Change is inevitable; therefore some type of change control process is mandatory for every project.
























                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   137


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   158   159   160   161   162   163   164   165   166   167   168