Page 168 -
P. 168

6 - PROJECT TIME MANAGEMENT






                         These processes interact with each other and with processes in other Knowledge Areas as described in detail
                      in Section 3 and Annex A1.

                         Distinguishing the project schedule presentation (schedule) from the schedule data (Section 6.6.3.3) and
                      calculations that produce the project schedule (Section 6.6.3.2) is practiced by referring to the scheduling tool
                      populated with project data as the schedule model. A schedule model is a representation of the plan for executing
                      the project’s activities including durations, dependencies, and other planning information, used to produce project
                      schedules along with other scheduling artifacts. For specific information regarding the schedule model, refer to the
                      Practice Standard for Scheduling. [8]

                         On some projects, especially those of smaller scope, defining activities, sequencing activities, estimating
                      activity resources, estimating activity durations, and developing the schedule model are so tightly linked that they
                      are viewed as a single process that can be performed by a person over a relatively short period of time. These
                      processes are presented here as distinct elements because the tools and techniques for each process are different.

                         The Project Time Management processes and their associated tools and techniques are documented in the
                      schedule management plan. The schedule management plan is a subsidiary plan of, and integrated with, the project
                      management plan through the Develop Project Management Plan process (Section 4.2), The schedule management
                      plan identifies a scheduling method and scheduling tool (Figure 6-2), and sets the format and establishes criteria
                      for developing and controlling the project schedule. The selected scheduling method defines the framework and
                      algorithms used in the scheduling tool to create the schedule model. Some of the better known scheduling methods
                      include critical path method (CPM) and critical chain method (CCM).

                         Project schedule development uses the outputs from the processes to define activities, sequence activities,
                      estimate activity resources, and estimate activity durations in combination with the scheduling tool to produce
                      the schedule model. The finalized and approved schedule is the baseline that will be used in the Control Schedule
                      process (Section 6.7). As the project activities are being performed, the majority of effort in the Project Time
                      Management Knowledge Area will occur in the Control Schedule process to ensure completion of project work in a
                      timely manner. Figure 6-2 provides a scheduling overview that shows how the scheduling method, scheduling tool,
                      and outputs from the Project Time Management processes interact to create a project schedule.



























             142      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   163   164   165   166   167   168   169   170   171   172   173