Page 171 -
P. 171

6 - PROJECT TIME MANAGEMENT






                    6.1 Plan Schedule Management

                     Plan Schedule Management is the process of establishing the policies, procedures, and documentation for
                   planning, developing, managing, executing, and controlling the project schedule. The key benefit of this process is
                   that it provides guidance and direction on how the project schedule will be managed throughout the project. The
                   inputs, tools and techniques, and outputs of this process are depicted in Figure 6-3. Figure 6-4 depicts the data
                   flow diagram of the process.


                                     Inputs            Tools & Techniques           Outputs
                                                                                                                          6
                              .1  Project management plan  .1  Expert judgment  .1  Schedule management
                              .2  Project charter     .2  Analytical techniques   plan
                              .3  Enterprise environmental    .3  Meetings
                                factors
                              .4  Organizational process
                                assets


                              Figure 6-3. Plan Schedule Management: Inputs, tools & techniques, and outputs





                                    4.1
                                 Develop Project         Project Time Management
                                   Charter
                                      • Project charter                                        11.2
                                                                  6.1                          Identify
                                                              Plan Schedule                    Risks
                                      • Project                Management
                                        management   • Enterprise
                                        plan       environmental
                                                    factors
                                    4.2           • Organizational   • Schedule
                                                                     management
                                 Develop Project    process assets    plan
                                                                                               11.4
                                 Management                                                    Perform
                                    Plan
                                                                                             Quantitative
                                                        6.2                6.4               Risk Analysis
                                                       Define          Estimate Activity
                                                       Activities        Resources
                                  Enterprise/
                                  Organization
                                                        6.3                6.5
                                                       Sequence        Estimate Activity
                                                                         Durations
                                                       Activities       • Change log
                                                                           6.6
                                                                          Develop
                                                                         Schedule




                                        Figure 6-4. Plan Schedule Management data Flow diagram








                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   145
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   166   167   168   169   170   171   172   173   174   175   176