Page 175 -
P. 175

6 - PROJECT TIME MANAGEMENT






                        •   rules of performance measurement. Earned value management (EVM) rules or other physical
                           measurement rules of performance measurement are set. For example, the schedule management plan
                           may specify:
                                   ○ Rules for establishing percent complete,

                                   ○ Control accounts at which management of progress and schedule will be measured,
                                   ○  Earned value measurement techniques (e.g., baselines, fixed-formula, percent complete, etc.)
                                   to be employed (for more specific information, refer to the Practice Standard for Earned Value
                                   Management) [9],
                                   ○  Schedule performance measurements such as schedule variance (SV) and schedule performance   6
                                   index (SPI) used to assess the magnitude of variation to the original schedule baseline.
                        •  reporting formats. The formats and frequency for the various schedule reports are defined.

                        •  Process descriptions. Descriptions of each of the schedule management processes are documented.


                   6.2 define Activities


                     Define Activities is the process of identifying and documenting the specific actions to be performed to produce
                   the project deliverables. The key benefit of this process is to break down work packages into activities that provide
                   a basis for estimating, scheduling, executing, monitoring, and controlling the project work. The inputs, tools and
                   techniques, and outputs of this process are depicted in Figure 6-5. Figure 6-6 depicts the data flow diagram of the
                   process.


                                     Inputs            Tools & Techniques           Outputs

                              .1  Schedule management    .1  Decomposition    .1  Activity list
                                plan                  .2  Rolling wave planning  .2  Activity attributes
                              .2  Scope baseline      .3  Expert judgment     .3  Milestone list
                              .3  Enterprise environmental
                                factors
                              .4  Organizational process
                                assets

                                    Figure 6-5. define Activities: Inputs, tools & techniques, and outputs






















                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   149
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   170   171   172   173   174   175   176   177   178   179   180