6 - PROJECT TIME MANAGEMENT












                                                            Project Time Management

                                                           6.1                 6.2
                                                        Plan Schedule         Define
                                                        Management           Activities
                                       5.3
                                      Define
                                      Scope                 • Schedule   • Activity list
                                                              management   • Activity attributes
                                                              plan       • Milestone list
                                         • Project scope
                                           statement
                                                                     6.3                         Project
                                                                   Sequence                     Documents
                                                                   Activities  • Project documents
                                         • Organizational                       updates
                                           process assets
                                         • Enterprise
                                          environmental                • Project schedule
                                           factors                      network diagrams

                                     Enterprise/
                                    Organization                     6.6
                                                                   Develop
                                                                   Schedule





                                               Figure 6-8. Sequence Activities data Flow diagram
                         Every activity and milestone except the first and last should be connected to at least one predecessor with a
                      finish-to-start or start-to-start logical relationship and at least one successor with a finish-to-start or finish-to-
                      finish logical relationship. Logical relationships should be designed to create a realistic project schedule. It may
                      be necessary to use lead or lag time between activities to support a realistic and achievable project schedule.
                      Sequencing can be performed by using project management software or by using manual or automated techniques.



                      6.3.1 Sequence Activities: Inputs



                      6.3.1.1 Schedule Management Plan

                         Described in Section 6.1.3.1. The schedule management plan identifies the scheduling method and tool to be
                      used for the project, which will guide how the activities may be sequenced.














             154      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   175   176   177   178   179   180   181   182   183   184   185