6 - PROJECT TIME MANAGEMENT
Project Time Management
6.1 6.2
Plan Schedule Define
Management Activities
5.3
Define
Scope • Schedule • Activity list
management • Activity attributes
plan • Milestone list
• Project scope
statement
6.3 Project
Sequence Documents
Activities • Project documents
• Organizational updates
process assets
• Enterprise
environmental • Project schedule
factors network diagrams
Enterprise/
Organization 6.6
Develop
Schedule
Figure 6-8. Sequence Activities data Flow diagram
Every activity and milestone except the first and last should be connected to at least one predecessor with a
finish-to-start or start-to-start logical relationship and at least one successor with a finish-to-start or finish-to-
finish logical relationship. Logical relationships should be designed to create a realistic project schedule. It may
be necessary to use lead or lag time between activities to support a realistic and achievable project schedule.
Sequencing can be performed by using project management software or by using manual or automated techniques.
6.3.1 Sequence Activities: Inputs
6.3.1.1 Schedule Management Plan
Described in Section 6.1.3.1. The schedule management plan identifies the scheduling method and tool to be
used for the project, which will guide how the activities may be sequenced.
154 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition
®
Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
This copy is a PMI Member benefit, not for distribution, sale, or reproduction.