Page 184 -
P. 184

6 - PROJECT TIME MANAGEMENT






                           •   discretionary dependencies. Discretionary dependencies are sometimes referred to as preferred logic,
                              preferential logic, or soft logic. Discretionary dependencies are established based on knowledge of best
                              practices within a particular application area or some unusual aspect of the project where a specific
                              sequence is desired, even though there may be other acceptable sequences. Discretionary dependencies
                              should be fully documented since they can create arbitrary total float values and can limit later scheduling
                              options.  When fast tracking techniques are employed, these discretionary dependencies should be
                              reviewed and considered for modification or removal. The project team determines which dependencies
                              are discretionary during the process of sequencing the activities.
                           •   External dependencies. External dependencies involve a relationship between project activities and
                              non-project activities. These dependencies are usually outside the project team’s control. For example,
                              the testing activity in a software project may be dependent on the delivery of hardware from an external
                              source, or governmental environmental hearings may need to be held before site preparation can begin
                              on a construction project. The project management team determines which dependencies are external
                              during the process of sequencing the activities.
                           •   Internal  dependencies. Internal dependencies involve a precedence relationship between project
                              activities and are generally inside the project team’s control. For example, if the team cannot test a
                              machine until they assemble it, this is an internal mandatory dependency. The project management team
                              determines which dependencies are internal during the process of sequencing the activities.


                      6.3.2.3 Leads and Lags

                         A lead is the amount of time whereby a successor activity can be advanced with respect to a predecessor
                      activity. For example, on a project to construct a new office building, the landscaping could be scheduled to start
                      two weeks prior to the scheduled punch list completion. This would be shown as a finish-to-start with a two-week
                      lead as shown in Figure 6-10. Lead is often represented as a negative value for lag in scheduling software.





                                                   Complete                              Write
                                                  Punch List                             Draft

                                   FS – 2 Weeks (Lead)                          SS – 15 Days (Lag)

                                                         Landscape                            Edit
                                                        Building Lot                          Draft




                                                    Figure 6-10. Examples of Lead and Lag











             158      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   179   180   181   182   183   184   185   186   187   188   189