6 - PROJECT TIME MANAGEMENT
A B
SS
C D E
FS + 15
Begin H F G End
SS + 10
I J
FF
K L
Figure 6-11. Project Schedule network diagram
6.3.3.2 Project documents updates
Project documents that may be updated include, but are not limited to:
• Activity lists,
• Activity attributes,
• Milestone list, and
• Risk register.
6.4 Estimate Activity resources
Estimate Activity Resources is the process of estimating the type and quantities of material, human
resources, equipment, or supplies required to perform each activity. The key benefit of this process is that it
identifies the type, quantity, and characteristics of resources required to complete the activity which allows
more accurate cost and duration estimates. The inputs, tools and techniques, and outputs of this process are
depicted in Figure 6-12. Figure 6-13 depicts the data flow diagram of the process.
160 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition
®
Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
This copy is a PMI Member benefit, not for distribution, sale, or reproduction.