6 - PROJECT TIME MANAGEMENT






                   6.4.1.4 resource calendars


                   Described in Sections 9.2.3.2 and 12.2.3.3. A resource calendar is a calendar that identifies the working
                   days and shifts on which each specific resource is available. Information on which resources (such as human
                   resources, equipment, and material) are potentially available during a planned activity period, is used for
                   estimating resource utilization. Resource calendars specify when and how long identified project resources
                   will be available during the project. This information may be at the activity or project level. This knowledge
                   includes consideration of attributes such as resource experience and/or skill level, as well as various
                   geographical locations from which the resources originate and when they may be available.
                                                                                                                          6

                   6.4.1.5 risk register


                     Described in Section 11.2.3.1. Risk events may impact resource selection and availability. Updates to the risk
                   register are included with project documents updates, described in Section 11.5.3.2, from Plan Risk Responses.


                   6.4.1.6 Activity cost Estimates

                     Described in Section 7.2.3.1. The cost of resources may impact resource selection.


                   6.4.1.7 Enterprise Environmental Factors

                     Described in Section 2.1.5.  The enterprise environmental factors that can influence the Estimate  Activity
                   Resources process include, but are not limited to, resource location, availability, and skills.


                   6.4.1.8 organizational Process Assets


                     Described in Section 2.1.4. The organizational process assets that can influence the Estimate Activity Resources
                   process include, but are not limited to:
                        •  Policies and procedures regarding staffing,

                        •  Policies and procedures relating to rental and purchase of supplies and equipment, and
                        •  Historical information regarding types of resources used for similar work on previous projects.




















                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   163


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   184   185   186   187   188   189   190   191   192   193   194