Page 182 -
P. 182

6 - PROJECT TIME MANAGEMENT






                      6.3.1.7 organizational Process Assets

                         Described in Section 2.1.4. The organizational process assets that can influence the Sequence Activities process
                      include, but are not limited to: project files from the corporate knowledge base used for scheduling methodology,
                      existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling
                      methodology that are considered in developing logical relationships, and templates that can be used to expedite the
                      preparation of networks of project activities. Related activity attributes information in templates can also contain
                      additional descriptive information useful in sequencing activities.


                      6.3.2 Sequence Activities: tools and techniques



                      6.3.2.1 Precedence diagramming Method

                         The precedence diagramming method (PDM) is a technique used for constructing a schedule model in which
                      activities are represented by nodes and are graphically linked by one or more logical relationships to show the
                      sequence in which the activities are to be performed. Activity-on-node (AON) is one method of representing a
                      precedence diagram. This is the method used by most project management software packages.

                         PDM includes four types of dependencies or logical relationships. A predecessor activity is an activity that
                      logically comes before a dependent activity in a schedule. A successor activity is a dependent activity that logically
                      comes after another activity in a schedule. These relationships are defined below and are illustrated in Figure 6-9:
                            •   Finish-to-start (FS). A logical relationship in which a successor activity cannot start until a predecessor
                              activity has finished. Example: The awards ceremony (successor) cannot start until the race (predecessor)
                              has finished.

                            •   Finish-to-finish (FF). A logical relationship in which a successor activity cannot finish until a predecessor
                              activity has finished. Example: Writing a document (predecessor) is required to finish before editing the
                              document (successor) can finish.

                            •   Start-to-start (SS). A logical relationship in which a successor activity cannot start until a predecessor
                              activity has started. Example: Level concrete (successor) cannot begin until pour foundation (predecessor)
                              begins.

                            •   Start-to-finish (SF). A logical relationship in which a successor activity cannot finish until a predecessor
                              activity has started. Example: The first security guard shift (successor) cannot finish until the second
                              security guard shift (predecessor) starts.















             156      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   177   178   179   180   181   182   183   184   185   186   187