Page 179 -
P. 179

6 - PROJECT TIME MANAGEMENT






                   6.2.3.2 Activity Attributes

                     Activities, distinct from milestones, have durations, during which the work of that activity is performed,
                   and may have resources and costs associated with that work. Activity attributes extend the description of
                   the activity by identifying the multiple components associated with each activity. The components for each
                   activity evolve over time. During the initial stages of the project, they include the activity identifier (ID), WBS ID,
                   and activity label or name, and when completed, may include activity codes, activity description, predecessor
                   activities, successor activities, logical relationships, leads and lags (Section 6.3.2.3), resource requirements,
                   imposed dates, constraints, and assumptions. Activity attributes can be used to identify the person responsible
                   for executing the work, geographic area, or place where the work has to be performed, the project calendar   6
                   the activity is assigned to, and activity type such as level of effort (often abbreviated as LOE), discrete effort,
                   and apportioned effort. Activity attributes are used for schedule development and for selecting, ordering, and
                   sorting the planned schedule activities in various ways within reports. The number of attributes varies by
                   application area.


                   6.2.3.3 Milestone List

                     A milestone is a significant point or event in a project. A milestone list is a list identifying all project milestones
                   and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those
                   based upon historical information. Milestones are similar to regular schedule activities, with the same structure and
                   attributes, but they have zero duration because milestones represent a moment in time.


                   6.3 Sequence Activities


                     Sequence Activities is the process of identifying and documenting relationships among the project activities. The
                   key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all
                   project constraints. The inputs, tools and techniques, and outputs of this process are depicted in Figure 6-7. Figure
                   6-8 depicts the data flow diagram of the process.


                                     Inputs            Tools & Techniques           Outputs
                              .1  Schedule management    .1  Precedence diagramming    .1  Project schedule network
                                plan                    method (PDM)           diagrams
                              .2  Activity list       .2  Dependency          .2  Project documents
                              .3  Activity attributes    determination         updates
                              .4  Milestone list      .3  Leads and lags
                              .5  Project scope statement
                              .6  Enterprise environmental
                                factors
                              .7  Organizational process
                                assets

                                  Figure 6-7. Sequence Activities: Inputs, tools & techniques, and outputs







                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   153
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   174   175   176   177   178   179   180   181   182   183   184