Page 176 -
P. 176

6 - PROJECT TIME MANAGEMENT












                                                                      Project Time Management

                                                                     6.1
                                                                  Plan Schedule
                                           5.4                    Management
                                           Create                                • Schedule
                                           WBS                                     management plan
                                             • Scope baseline
                                                                              6.2
                                                                             Define
                                                                             Activities
                                             • Organizational
                                               process assets
                                             • Enterprise
                                              environmental
                                               factors          • Milestone      • Activity list
                                                                  list           • Activity attributes
                                         Enterprise/
                                         Organization                6.3                6.5
                                                                   Sequence         Estimate Activity
                                                                    Activities        Durations

                                                                     6.4                6.6
                                                                  Estimate Activity   Develop
                                                                   Resources         • Change log
                                                                                      Schedule





                                                Figure 6-6. define Activities data Flow diagram

                         Implicit in this process are defining and planning the schedule activities such that the project objectives will
                      be met. The Create WBS process identifies the deliverables at the lowest level in the WBS—the work package.
                      Work packages are typically decomposed into smaller components called activities that represent the work effort
                      required to complete the work package.



                      6.2.1 define Activities: Inputs


                      6.2.1.1 Schedule Management Plan

                         Described in Section 6.1.3.1. A key input from the schedule management plan is the prescribed level of detail
                      necessary to manage the work.













             150      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   171   172   173   174   175   176   177   178   179   180   181