6 - PROJECT TIME MANAGEMENT








                                                              Project Time
                                                          Management Overview

                               6.1 Plan Schedule                       6.3 Sequence    6.4 Estimate Activity
                                 Management      6.2 Define Activities  Activities         Resources
                             .1 Inputs          .1 Inputs          .1 Inputs           .1 Inputs
                               .1 Project management plan    .1 Schedule management        .1 Schedule management        .1 Schedule management
                               .2 Project charter     plan            plan                plan
                               .3 Enterprise environmental      .2 Scope baseline    .2 Activity list    .2 Activity list
                                factors           .3 Enterprise environmental      .3 Activity attributes    .3 Activity attributes
                               .4 Organizational process         factors    .4 Milestone list    .4 Resource calendars
                                assets            .4 Organizational process        .5 Project scope statement    .5 Risk register
                                                   assets            .6 Enterprise environmental               .6 Activity cost estimates
                             .2 Tools & Techniques                    factors            .7 Enterprise environmental
                               .1 Expert judgment  .2 Tools & Techniques    .7 Organizational process         factors     6
                               .2 Analytical techniques    .1 Decomposition    assets    .8 Organizational process
                               .3 Meetings        .2 Rolling wave planning               assets
                                                  .3 Expert judgment  .2 Tools & Techniques
                             .3 Outputs                              .1 Precedence diagramming    .2 Tools & Techniques
                               .1 Schedule management      .3 Outputs    method (PDM)
                                plan              .1 Activity list    .2 Dependency determination    .1 Expert judgment
                                                                                         .2 Alternative analysis
                                                  .2 Activity attributes    .3 Leads and lags    .3 Published estimating data
                                                  .3 Milestone list
                                                                   .3 Outputs            .4 Bottom-up estimating
                              6.5 Estimate Activity                  .1 Project schedule network    .5 Project management
                                                                                          software
                                  Durations                           diagrams
                                                 6.6 Develop Schedule    .2 Project documents updates  .3 Outputs
                             .1 Inputs                                                   .1 Activity resource
                               .1 Schedule management                                     requirements
                                plan            .1 Inputs                                .2 Resource breakdown
                               .2 Activity list    .1 Schedule management      6.7 Control Schedule    structure
                               .3 Activity attributes     plan                           .3 Project documents
                               .4 Activity resource         .2 Activity list              updates
                                requirements      .3 Activity attributes  .1 Inputs
                               .5 Resource calendars    .4 Project schedule network      .1 Project management plan
                               .6 Project scope statement     diagrams    .2 Project schedule
                               .7 Risk register    .5 Activity resource         .3 Work performance data
                               .8 Resource breakdown         requirements    .4 Project calendars
                                structure         .6 Resource calendars    .5 Schedule data
                               .9 Enterprise environmental      .7 Activity duration estimates    .6 Organizational process
                                factors           .8 Project scope statement    assets
                                .10 Organizational process        .9 Risk register  .2 Tools & Techniques
                                assets             .10 Project staff assignments
                                                   .11 Resource breakdown        .1 Performance reviews
                             .2 Tools & Techniques     structure     .2 Project management
                               .1 Expert judgment    .12  Enterprise environmental      software
                               .2 Analogous estimating     factors    .3 Resource optimization
                               .3 Parametric estimating    .13 Organizational process         techniques
                               .4 Three-point estimating     assets    .4 Modeling techniques
                               .5 Group decision-making              .5 Leads and lags
                                      techniques  .2 Tools & Techniques    .6 Schedule compression
                               .6 Reserve analysis    .1 Schedule network analysis    .7 Scheduling tool
                                                  .2 Critical path method
                             .3 Outputs           .3 Critical chain method  .3 Outputs
                               .1 Activity duration estimates    .4 Resource optimization        .1 Work performance
                               .2 Project documents updates     techniques     information
                                                  .5 Modeling techniques    .2 Schedule forecasts
                                                  .6 Leads and lags    .3 Change requests
                                                  .7 Schedule compression    .4 Project management plan
                                                  .8 Scheduling tool     updates
                                                                     .5 Project documents updates
                                                .3 Outputs           .6 Organizational process
                                                  .1 Schedule baseline    assets updates
                                                  .2 Project schedule
                                                  .3 Schedule data
                                                  .4 Project calendars
                                                  .5 Project management plan
                                                   updates
                                                  .6 Project documents updates
                                             Figure 6-1. Project time Management overview



                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   143
                                                                                       ®