9 - PROJECT HUMAN RESOURCE MANAGEMENT






                           •   Knowledge. Consider if the team member has relevant knowledge of the customer, similar implemented
                              projects, and nuances of the project environment.
                           •   Skills. Determine whether the member has the relevant skills to use a project tool, implementation, or
                              training.

                           •  Attitude. Determine whether the member has the ability to work with others as a cohesive team.
                           •  International factors. Consider team member location, time zone and communication capabilities.


                      9.2.3 Acquire Project team: outputs



                      9.2.3.1 Project Staff Assignments

                         The project is staffed when appropriate people have been assigned to the team. The documentation of these
                      assignments can include a project team directory, memos to team members, and names inserted into other parts
                      of the project management plan, such as project organization charts and schedules.


                      9.2.3.2 resource calendars


                         Resource calendars document the time periods that each project team member is available to work on the project.
                      Creating a reliable schedule (Section 6.6.3.1) depends on having a good understanding of each person’s availability
                      and schedule constraints, including time zones, work hours, vacation time, local holidays, and commitments to
                      other projects.


                      9.2.3.3 Project Management Plan updates


                         Elements of the project management plan that may be updated include, but are not limited to, the human
                      resource management plan. For example, the person assigned to a predefined role may not fulfill all staffing
                      requirements outlined in the human resource management plan. When gaps occur, the project management plan
                      needs to be updated to change the team structure, roles, or responsibilities.

























             272      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®