12 - PROJECT PROCUREMENT MANAGEMENT












                                                      Project Procurement Management
                                                                 12.1
                                                                 Plan
                                                               Procurement
                                                               Management

                                                                   • Procurement
                                                                    documents

                                    4.2                          12.4
                                 Develop Project                 Close                      Enterprise/
                                  Management                  Procurements                  Organization
                                    Plan          • Project                • Organizational
                                                    management                process assets
                                                    plan                      updates
                                                                           • Closed
                                                                              procurements




                                                                                                                          12
                                           Figure 12-9. close Procurements data Flow diagram

                     The Close Procurements process also involves administrative activities such as finalizing open claims, updating
                   records to reflect final results, and archiving such information for future use. Close Procurements addresses each
                   contract applicable to the project or a project phase. In multiphase projects, the term of a contract may only be
                   applicable to a given phase of the project. In these cases, the Close Procurements process closes the procurement(s)
                   applicable to that phase of the project. Unresolved claims may be subject to litigation after closure. The contract
                   terms and conditions can prescribe specific procedures for agreement closure. The Close Procurements process
                   supports the Close Project or Phase process (Section 4.6) by ensuring contractual agreements are completed or
                   terminated.

                     Early termination of a contract is a special case of procurement closure that can result from a mutual agreement
                   by both parties, from the default of one party, or for convenience of the buyer if provided for in the contract. The
                   rights and responsibilities of the parties in the event of an early termination are contained in the terminations clause
                   of the contract. Based upon those procurement terms and conditions, the buyer may have the right to terminate
                   the whole contract or a portion of the contract, at any time, for cause or convenience. However, based upon those
                   contract terms and conditions, the buyer may have to compensate the seller for seller’s preparations and for any
                   completed and accepted work related to the terminated part of the contract.














                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   387
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   408   409   410   411   412   413   414   415   416   417   418